PMF modifications at hydroelectric plants

About this project

client
Confidential power client
location
Michigan
cost
$175,000 (Barr's fees)
completion date
2007-2008; 2017-2020

The Federal Energy Regulatory Commission (FERC) directed this confidential client to increase spill capacity at three of its hydroelectric facilities in order to pass the probable maximum flood (PMF). Barr performed a feasibility study to identify a cost-effective solution for modifying the plants to pass the PMF. We developed several possibilities for each plant, along with preliminary cost estimates.

For the first plant, the client selected Barr’s recommended plan to raise the embankment corewall and modify the tainter-gate spillway hoisting to increase the gate opening. The design was approved by FERC and constructed in 2008. In addition, we designed a downstream-embankment earthen buttress and concrete retaining wall to increase the embankment stability and meet FERC criteria for the PMF load case.

For the other two plants, Barr evaluated several major options, including constructing a new concrete spillway, installing a new headgate in an existing abandoned bay, and making significant modifications to the tainter-gate hoist. The work was initially estimated to cost hundreds of thousands of dollars, but by thoughtfully considering site features and conducting a detailed review of the hydraulics necessary to pass the required flow, we were able to develop a simplified plan that still achieved the primary goals of protecting the powerhouses from flooding and passing the PMF flow without overtopping the embankments. The design consisted of a small floodwall to divert some excess flow around the powerhouse and back to the river at the downstream end of the spillway. This solution cost a fraction of the amount of the original options. FERC approved the proposed plans and modifications, and construction took place in 2020.

Key team members

Bethany Kelly

Vice President
Senior Geotechnical Engineer

Chris Toulouse

Senior Structural Engineer

Tor Hansen

Vice President
Senior Civil Engineer

John Quist

Vice President
Senior Civil Engineer

Related Hydro projects

Air dispersion modeling for distributed-generation plant
Park and landscape design for Mouse River enhanced flood protection project
Third-party transmission-line construction monitoring
Design of abutment wall extension at Dells hydro station
Coffee Creek trout stream restoration
Dry-stack tailings management
Tailings basin expansion and closure options
Investigation and remediation of jet-fuel release
Vapor intrusion investigation and mitigation in a residential neighborhood
Engineering services and permitting assistance for Bison 2 and 3 wind farms
Dam safety consultations for SaskPower
Geotechnical, structural, and civil work for Canadian wind farm
Snowpack monitoring and lake drawdown for Minnesota watershed district
Electric-energy resource options study
Design services for solar generation facility
Penn Avenue sinkhole investigation and rehabilitation
Study of engineering risks and site feasibility for windpower client
Landslide stabilization design for an underground coal mine
Advanced oxidation process pilot evaluation for municipal drinking-water system
Environmental review for proposed natural-gas pipeline
EMIS implementation and related assistance
RICE applicability analysis and audit
Installation of new auxiliary boilers for power plant
Responding to wind-farm tornado damage
Evaluation of wind-turbine foundation following fire damage
Engine compliance tool update
Test burn for cofiring coal and biomass
Transmission line EIS
Groundwater modeling for wellhead-protection-plan amendment
Multi-site PFAS remedial investigation and remediation
Sediment removal from beneath Vermillion River bridge
Monitoring of end-pit lake at oil sands mine
Permitting and wetland delineation for a community solar garden
Penstock replacement at McClure Dam
Flood risk reduction of suburban lakes
Letter of map revision for Minnesota city
Options study and design to restore biomass fuel-handling system
Mine remediation and reclamation
Air permit-to-install strategy and application
Steam-line evaluation at Rapids Energy Center
Air quality permitting for distributed-generation plant
Site reviews for solar gardens across Minnesota
West River Parkway landslide repair
FERC relicensing of Ford Lake Dam
Groundwater compliance assistance for CCR Rule
Developing health assessment tools for wind-turbine towers and foundations
Condition assessment and options study for hydro facility
Floodproofing of utility switchyard
Environmental review and permitting for natural-gas-distribution projects
Flood mitigation at refinery
Wetland replacement assistance for highway project
Environmental support for post-fire cleanup at industrial facility
Environmental review for peaking plants
Lilydale Regional Park stormwater management and slope stabilization
PFOS investigation at municipal wastewater plant
Engineering and design services for new truck dumper
Response to denatured ethanol release
Aquatic invasive species (AIS) management in a Wisconsin lake
Solar-energy-system compliance
Berm-failure study at saltwater disposal well site
Auxiliary boiler installation
Preliminary feasibility study for PFAS-related water quality concerns
Rockford dam removal
Retrofit engineering for ash conveyance
Groundwater modeling and remedial improvements at closed landfills
Stressor-identification report for an impaired urban stream
Energy integration study for waste-heat utilization
Environmental services for coal-yard decommissioning
Post-flood stream assessment and natural channel design
Option study and design for air jig dewatering system
Permitting, design, and construction oversight for CCR surface impoundment
Transmission-line permitting assistance
Structural and electrical engineering for coal-dryer load-out improvements
Environmental review for natural gas pipelines
Poplar Bluff substation upgrade
Transmission line upgrades for reliable power delivery
arc-flash analysis at Coal Creek Station
Study of solar developments on closed Minnesota landfills
Geotechnical investigation for the East Valley Battery Storage Facility
Geotechnical investigation of pumped-storage hydroelectric facility
Preliminary geotechnical engineering and geophysical investigation
Seneca solar project geotechnical engineering services
Conceptual development for Coal FIRST initiative
Pre-FEED study for Coal FIRST initiative
Civil engineering services for 10 MW solar facility
Structural analysis and evaluation of powerhouse
Water-quality and structural monitoring for channel dredging
Permitting assistance for partial repowering of wind facility
Environmental review and permitting for windfarm repowering
Mitigation of aerosol impacts from coal combustion
Spillway redesign at Cedar Falls Hydro Generating Station
Hydropower facility evaluation and improvement recommendations
Flood risk management system upgrades and FEMA certification
Design for spillway replacement at Bond Falls Dam
Crane walk geotechnical engineering at Kings Point wind site
PMF study for the Dead River
Cyclic degradation geotechnical evaluation for wind turbine foundations
PFAS mass balance and sample collection
PFAS treatment during power plant decommissioning
TMDL study and water quality assessment for a suburban stream
Gate upgrade at Island Lake Dam
Solar on reclaimed coal mine, settlement and subsidence risk analysis
Gas processing equipment, outage procedure and fitness-for-service evaluation
PFAS stack testing services for a manufacturing client
AWIA risk and emergency compliance for urban drinking water
Environmental assessment program for highway safety improvements
CFD modeling of stormwater tunnels
Environmental services at manufacturing facility
Design of repairs to leaking reservoir
Trichloroethylene (TCE) investigation and remediation
RCRA waste tank inspection, certification, and closure
Environmental support for solar power facilities
Desktop study and geotechnical investigation for new wind power site
Air permitting assistance for reaction-injection molding operation
Wind farm repowering structural assessment
Road raise and conceptual design
Renewable energy development plan
Carbon-capture-system feasibility study
Reasonably available control technology analysis for refinery
Flood-control-system upgrades and certification
Landslide stabilization protects architectural treasures
Strategy for collecting lake-morphometry data
Tailings facility dam safety review
Implementing a dual fuel system for peaking plant
Comprehensive water audits at manufacturing facilities